
Priority Projects
The Virgin Islands Office of Disaster Recovery’s Top Projects Page provides the status on priority recovery projects and establishes a continuous point of information to the general public. The top projects are determined by the following criteria:
Featured Projects
Featured
Governor Juan F. Luis Hospital
Featured
Charlotte Amalie High School (Reconstruction)
Featured
Altona Lagoon Bridge
*Updated 6.30.25*
Sort/Filter Projects by
Search by Sector
Filter by Alphabet:
Project Name
Private: Administration Building
Project Description
Demolition & replacement of the Administration Building with a two-story building.
Funding Source
GVI Agency
Department of Agriculture
Target Start Date
May 2026
Target Completion Date
May 2028
Estimated Project Cost
$4,997,247
Location
St. Croix
Project Phase
In Design
Please note: The start and end dates for projects in or that have not started construction are target dates and are subject to change.
