ST. THOMAS, USVI – The Virgin Islands Department of Education (VIDE) continues to make important progress on a number of projects related to the new construction and/or modernization of the Territory’s public schools.

 

ST. CROIX DISTRICT

Arthur A. Richards Jr. High School Demolition
Demolition is well underway and will continue for the next eight months at the Arthur A. Richards Jr. High School (now Arthur A. Richards K-8 School), which was destroyed by Hurricanes Irma and Maria in 2017. All permits were acquired successfully from the Department of Planning and Natural Resources. The contractor is Consolidated Asphalt and Civil Works LLC. Weekly meetings are held with the contractor, VIDE personnel and the Department of Public Works to ensure the proper execution of the project. The goal is to relocate the Arthur A. Richards PreK-8 School to the current site of the Evelyn M. Williams Elementary School. Global design firm, the DLR Group, has been preparing the bridging documents that allows the VIDE to commence the solicitation process of procuring an architectural design firm as part of a design-build team to work on the official design of the new Arthur A. Richards PreK-8 campus. Arthur A. Richards will be the first site in the territory that receives costing from FEMA for its replacement.

Evelyn M. Williams Elementary School Demolition
The demolition of Evelyn M. Williams Elementary School, which was shuttered in 2015 due to irreparable structural damage, is expected to be completed by December 2021. The selected vendor for this project is Eleven Construction. Once funding has been acquired, work can commence at any time without interruption because the site is currently unoccupied. The DLR Group has been
preparing the bridging documents, as Evelyn Williams will be the new site of the Arthur A. Richards PreK-8 School.

 

ST. THOMAS-ST. JOHN DISTRICT

Raphael O. Wheatley Skills Center Modernization
The contract for the modernization of the building that currently houses the Raphael O. Wheatley Skills Center has been signed by Governor Albert Bryan Jr., and was awarded to Custom Builders following the competitive bidding process. This site will be retrofitted to accommodate 9th grade students from Charlotte Amalie High School’s Building C when in-person instruction resumes. The Gladys Abraham Elementary School site will be the new location of the Skills Center. Walk-throughs of the Gladys Abraham site have been conducted and measures are being put in place to ensure adequate renovations are made to accommodate all Skills Center programs and to install adequate security features for the safety of students and staff.

Gladys Abraham Elementary School Modernization
The contract for the modernization of Gladys Abraham Elementary School, which will be the new site of the Skills Center, has been drafted and is pending funding to move forward. The winning contractor for the project is Custom Builders. The Gladys Abraham site will be the first site that is modernized and will be used to display the incorporation of the Industry Standards. Learn more about the VIDE’s Industry Standards at www.newschoolsvide.com.

Charlotte Amalie High School Demolition
The contract for the demolition of the Charlotte Amalie High School is pending funding before work can begin. The winning contractor for the project is Grade All. The contractor stands ready to begin, as soon as the funding has been secured. Funding challenges are the result of outstanding reimbursements from FEMA to the VIDE. The review process is complex, and ensuring the VIDE has the proper verification and documentation required by FEMA remains a critical component.

Temporary Curriculum Center at the Gramboko Building
FEMA has approved the use of the Gramboko Building as the temporary site of the Curriculum Center in the St. Thomas-St. John District. Currently, the project worksheet is moving through the approval process with FEMA. Once obligated, the RFP will be solicited for a contractor. This project has already been scoped and is ready to procure. The goal is to complete the project by December of 2021.