Project Name
Arthur A. Richards PK-8 School
Project Description
Construction of the new Arthur A. Richards PK-8 School.
Funding Source
GVI Agency
VI Department of Education
Target Start Date
Feb 2022
Target Completion Date
Jul 2026
Estimated Project Cost
$159,283,114
Location
St. Croix
Project Phase
In Construction