Priority Projects

The Virgin Islands Office of Disaster Recovery’s Top Projects Page provides the status on priority recovery projects and establishes a continuous point of information to the general public. The top projects are determined by the following criteria:

Featured Projects

*Updated 6.30.25*

Sort/Filter Projects by

Search by Sector

Project Name
Carlton Road
Project Description
Roadway reconstruction, rehabilitation and drainage improvements to Estate Carlton Road in Frederiksted.
GVI Agency
Department of Public Works
Target Start Date
Mar 2021
Target Completion Date
May 2022
Estimated Project Cost
$54,693
Location
St. Croix
Project Phase
In Close-Out

Sort/Filter Projects by

All Projects expand

Loading…

Project NameReplacement of GJFL Building
Project DescriptionDemolition & Replacement Re-Build of the Governor Juan F. Luis Hospital
Funding SourcePA
GVI AgencyGovernor Juan F. Luis Hospital
Target Start Date2/1/2021
Target Completion Date10/1/2031
Estimated Project Cost$931,940,469.10
LocationSt. Croix
Project PhaseSolicitation-Construction

Please note: The start and end dates for projects in or that have not started construction are target dates and are subject to change

Please note: The start and end dates for projects in or that have not started construction are target dates and are subject to change.