Project Name
Jersey Bay & Smith Bay Watershed Combined
Project Description
Repairs to roads in Jersey Bay & Smith Bay.
Funding Source
GVI Agency
Department of Public Works
Target Start Date
Jan 2025
Target Completion Date
Dec 2025
Estimated Project Cost
$7,071,411
Location
St. Thomas
Project Phase
In Design