Priority Projects
The Virgin Islands Office of Disaster Recovery’s Top Projects Page provides the status on priority recovery projects and establishes a continuous point of information to the general public. The top projects are determined by the following criteria:
Featured Projects
Featured Projects
Featured
Governor Juan F. Luis Hospital
Featured
Charlotte Amalie High School (Reconstruction)
Featured
Altona Lagoon Bridge
*Updated 6.30.25*
Sort/Filter Projects by
Search by Sector
Filter by Alphabet:
Project Name
Neighborhood Convenience Centers (7)
Project Description
The construction of Neighborhood Convenience Centers to address the issue of excessive waste generated after hurricanes.
Funding Source
GVI Agency
Virgin Islands Waste Management Authority
Target Start Date
Apr 2024
Target Completion Date
Jun 2025
Estimated Project Cost
$19,600,000
Location
Territory Wide
Project Phase
In Design
| Project Name | Replacement of GJFL Building |
|---|---|
| Project Description | Demolition & Replacement Re-Build of the Governor Juan F. Luis Hospital |
| Funding Source | PA |
| GVI Agency | Governor Juan F. Luis Hospital |
| Target Start Date | 2/1/2021 |
| Target Completion Date | 10/1/2031 |
| Estimated Project Cost | $931,940,469.10 |
| Location | St. Croix |
| Project Phase | Solicitation-Construction |
tesing1Please note: The start and end dates for projects in or that have not started construction are target dates and are subject to change
Please note: The start and end dates for projects in or that have not started construction are target dates and are subject to change.