Priority Projects
The Virgin Islands Office of Disaster Recovery’s Top Projects Page provides the status on priority recovery projects and establishes a continuous point of information to the general public. The top projects are determined by the following criteria:
Featured Projects
Featured
Governor Juan F. Luis Hospital
Featured
Altona Lagoon Bridge
Featured
Administration Building
*Updated 6.30.25*
Sort/Filter Projects by
Search by Sector
Filter by Alphabet:
Project Name
JFL Permanent Facility
Project Description
Construction of the JFL Permanent Facility
Funding Source
GVI Agency
Governor Juan F Luis Hospital
Target Start Date
Mar 2025
Target Completion Date
Mar 2031
Estimated Project Cost
927,190,469
Location
St. Croix
Project Phase
In Construction
Please note: The start and end dates for projects in or that have not started construction are target dates and are subject to change.