Priority Projects

The Virgin Islands Office of Disaster Recovery’s Top Projects Page provides the status on priority recovery projects and establishes a continuous point of information to the general public. The top projects are determined by the following criteria:

Featured Projects

*Updated 6.30.25*

Sort/Filter Projects by

Search by Sector

Project Name
Administration Building
Project Description
Demolition & replacement of the Administration Building with a two-story building.
GVI Agency
Department of Agriculture
Target Start Date
May 2026
Target Completion Date
May 2028
Estimated Project Cost
4,997,247
Location
St. Croix
Project Phase
In Design

Please note: The start and end dates for projects in or that have not started construction are target dates and are subject to change.

Popup Image