Project Name
JFL North
Project Description
Construction of a temporary hospital, administration building and parking lot.
GVI Agency
Governor Juan F. Luis Hospital
Target Start Date
Mar 2019
Target Completion Date
Dec 2023
Estimated Project Cost
$75,540,960
Location
St. Croix
Project Phase
Completed