Priority Projects

The Virgin Islands Office of Disaster Recovery’s Top Projects Page provides the status on priority recovery projects and establishes a continuous point of information to the general public. The top projects are determined by the following criteria:

Featured Projects

*Updated 6.30.25*

Sort/Filter Projects by

Search by Sector

St. Croix (57) arrow
Project Name
St. Croix Undergrounding
Project Description
Undergrounding of electrical utilities in multiple locations on St. Croix.
GVI Agency
Virgin Islands Water & Power Authority
Target Start Date
Apr 2021
Target Completion Date
Sep 2023
Estimated Project Cost
16,714,787
Location
St. Croix
Project Phase
Completed

Please note: The start and end dates for projects in or that have not started construction are target dates and are subject to change.

Popup Image