Priority Projects

The Virgin Islands Office of Disaster Recovery’s Top Projects Page provides the status on priority recovery projects and establishes a continuous point of information to the general public. The top projects are determined by the following criteria:

Featured Projects

*Updated 6.30.25*

Sort/Filter Projects by

Search by Sector

St. Croix (57) arrow
Project Name
Jersey Bay & Smith Bay Watershed Combined
Project Description
Repairs to roads in Jersey Bay & Smith Bay.
GVI Agency
Department of Public Works
Target Start Date
Jan 2025
Target Completion Date
Dec 2025
Estimated Project Cost
$7,071,411
Location
St. Thomas
Project Phase
In Design

Please note: The start and end dates for projects in or that have not started construction are target dates and are subject to change.

Popup Image