D. Hamilton & Alphonso “Piggy” Gerard Revitalization
Project Description
Revitalization of the David Hamilton Jackson Terrace and Alphonso “Piggy” Gerard Housing Communities
GVI Agency
VI Housing Authority
Target Start Date
Jan 2025
Target Completion Date
Dec 2026
Estimated Project Cost
121,059,237
Location
St. Croix
Project Phase
In Construction

Please note: The start and end dates for projects in or that have not started construction are target dates and are subject to change.