Whim Museum Buildings & Contents
Project Description
Repairs to Whim Museum – Great House to restore facilities back to pre-disaster design, function and capacity (in-kind) within the existing footprint.
GVI Agency
St. Croix Landmarks Society
Target Start Date
Jun 2026
Target Completion Date
Jul 2028
Estimated Project Cost
$1,502,734
Location
St. Croix
Project Phase
In Design