After general contractor selection the roles and responsibilities with respect to preconstruction and construction activities will be further defined. This solicitation includes the Construction Documents (CDs) package, which will be forwarded to interested general contractors upon request. The solicitation schedule is as follows:
ITEM TASK DATE
1 Bid Solicitation Notice Wednesday, December 15, 2021
2 Bid Package Release Wednesday, December 22, 2021
3 Pre-Bid Meeting Tuesday, January 11, 2022
4 Deadline for Questions Monday, January 31, 2022
5 Addenda Release/Response to Contractor Questions Friday, February 11, 2022
6 Contractor Bid Submittal * NEW DATE: February 25, 2022*
7 Bid Evaluation and Contractor Selection Friday, February 25, 2022
8 Pre-Construction Period (value engineering/negotiate
construction contract) START Monday, February 28, 2022
9 Construction TENTATIVE START Monday, July 25, 2022
10 Construction TENTATIVE FINISH Friday, August 30, 2024