January 27, 2023

 

 

 

WAPA Governing Board Approves Multiple Action Items; Wartsila Project Nearing Completion

U.S. VIRGIN ISLANDS – The Virgin Islands Water and Power Authority (“WAPA” or “Authority”) Governing Board today approved several action items to move three significant projects forward.

Today’s approvals saw the Governing Board approve a time extension to March 31, 2023, and a cost increase of $1,115,908.23 for the SC-33-20 -RHPP Wartsila New Generation Project. This project is completely funded through the US Department of Housing and Urban Development. The time extension will allow contractors to continue construction, and mechanical and electrical installation efforts for the project. The cost increase will provide the funding to allow contractors to complete necessary civil work related to the Battery Energy Storage System (BESS). The new Wartsila engines and BESS will benefit the Authority by providing an increase in efficient power generation and stability for the island of St. Thomas.

The second item approved was a time extension for the Authority’s Clifton Hill Project, SC-33-21. During the construction phase, project underwent delays to ensure coordination with the Department of Public Works. Department of Public Works will need to relocate and regrade the road in the remaining project area prior to the waterline installation. The new completion date is July 1, 2023. The Clifton Hill Water Rehabilitation Project is currently 87% complete.

Third on the Governing Board agenda was the approval to extend Barkley Technologies’ contract SC-26-21. This contract entails project management and design services for the Authority’s Composite Pole Project. The extension is for one additional year which will extend the contract end time to February 23, 2024, at a cost of $1,572,872.70. This project is being funded 90% by Federal Emergency Management Agency and 10% by the US Department of Housing and Urban Development. The installation of the composite poles territory-wide will provide hardening to the transmission and distribution infrastructure, making it more resilient and immune to damage from natural disasters. Composite Pole Project completion is 79% on St. Thomas, 73% on St. Croix and 79% on St. John.

“The Authority remains committed to providing more communication on ongoing projects designed to improve the reliability of our services. Through collaborative work with our partners, we look forward to increasing overall efficiency and transparency,” highlights Andrew Smith, CEO/Executive Director at the Authority.
###
.